Figure 1. Site before construction showing grading problems and consequent erosionProject Background
The construction of the infiltration trench began in the spring of 2004, and monitoring was initiated in July. The BMP was constructed in a small area between an academic building and a parking garage. The area was considered unsightly by the university because of poor grading (Figure 1).The design for the infiltration trench BMP included three main components. First, the site’s basic stormwater functions were to collect and infiltrate runoff from the upper deck of the adjacent bi-level parking garage. Second, the site was designed to provide sufficient research and demonstration opportunities to study the BMP’s hydrologic and water-quality performance. Third, the infiltration trench was designed to improve the site’s aesthetic appeal and function for the university.Initial Site Investigations
Originally the site was chosen because of its proximity to the parking garage. The garage is used only by university staff and does not receive any large truck or delivery traffic, so there is little chance of a major hazardous spill. More investigation was required, first to ensure that the general area was appropriate for such a BMP and later to determine the specific location and orientation of the trench. University plans were collected in an effort to determine the various existing utilities and infrastructure in the area. This was a particularly arduous task, because although plans existed for both the garage and the academic building, there were no plans specific to the common area between them. Onsite investigation proved to be the only reliable method. The grassed area contained three large electrical conduits, which were encased in concrete; one single telephone line; two stormwater conduits; and an existing stormwater inlet–a surprisingly dense network of utilities for a grassed area only 45 feet wide. Ultimately it was the locations of these utilities that determined the exact size, location, and orientation of the trench.During the early stages of the design process, a site investigation and feasibility study was performed. The results of this process showed that the site was suitable for the installation of an infiltration trench. First a test pit was dug to determine the depth to bedrock or water table and to classify the local soil properties and their suitability for stormwater infiltration. The depth to bedrock in the test pit was approximately 6 feet. Several authors recommend that 4 feet of soil are desirable between the bottom of an infiltration BMP and bedrock. Therefore, the 6-foot depth to bedrock in the test pit was a concern. Based on the location and elevation of a nearby first-order stream, the depth to groundwater was estimated to be about 15 feet. The test pit showed that there were 18 inches of disturbed topsoil followed by an equally thick layer of undisturbed and heavily weathered schist. The bottom 3 feet of the soil profile were dominated by a light tan sand layer that appeared to have excellent potential for infiltration. Soil samples were also taken from this layer and later analyzed in a laboratory setting. The particle size distribution of the soil sample classified the material as a loamy sand according to the Soil Conservation Service Soil Texture Triangle. An undisturbed 2-foot-deep step was left in the sand layer in which to perform some basic infiltration tests.A constant-head infiltrometer was used in the test pit to estimate the soil’s infiltration capacity. The apparatus consists of a 6-inch-diameter metal ring, which is hammered into the soil to a depth of 3 inches. A long, graduated water supply tube stands on top of the ring and maintains a constant 6 inches of head on the soil surface. The flow rate is then calculated directly using the graduations and a stopwatch. The percolation test showed that the soil was able to absorb water a rate of 8.1 inches per hour. The three-dimensional flow characteristics associated with this type of infiltration test seem to be more appropriate for the infiltration trench than they would be for some of the other infiltration BMPs at Villanova. The trench is relatively small and deep, and the near-vertical walls of the trench likely are responsible for a large portion of the infiltration. Other infiltration BMPs that have a larger and flatter soil-water interface seem to exhibit infiltration rates closer to the soil’s hydraulic conductivity; this is often much lower than a standard “percolation test” would suggest.
As previously stated, the first design objective of the infiltration trench was its stormwater function. However, because of the project’s research and demonstration goals, there were many measures taken that were specific to the site’s monitoring and demonstration purposes. These features include the installation of two monitoring wells in the trench (Figure 2). Both wells contain a pair of groundwater samplers, one at 2 feet and one at 4 feet beneath the bottom of the trench in the undisturbed subsoil. One well houses a pressure transducer, which enables the depth in the bed to be monitored. Another monitoring-specific feature is the bench located against the wall of the parking garage as shown in Figure 3. This bench houses a small grit and trash separator, a baffle, and a V-notch weir. The weir, in conjunction with a second pressure transducer, allows for continuous inflow monitoring. The top of the bench is locked and mounted on hinges for maintenance and demonstration purposes. A tipping bucket rain gauge was also installed on the upper level of the parking garage. All the instrumentation is wired to a datalogger located in a secure area of the garage. Finally, information signage has been installed at the site.
One lesson learned during the construction arose when the crushed stone arrived at the site for installation. The stone was specified to be “clean washed.” However, the stone clearly had not been washed and contained fine sediment that could decrease the life expectancy of the BMP. Fortunately, this was noticed before placement of the stone. The dump truck was then driven to a contained area where the bed was inclined and the stone was washed by a worker using a hose. Although this process was time consuming, it was absolutely imperative that the stone not contain significant amounts of fine-particle-size sediment. This experience illustrates the importance of both clear specifications and, most importantly, onsite supervision at similar BMP construction sites. A comprehensive site investigation is very important, especially if the project is a retrofit and there is a possibility of encountering existing utilities. In all, very few problems were encountered during the construction of the infiltration trench. This demonstrates the importance of proper siting, a thorough site investigation, and sound design.The infiltration trench is reducing erosive storm flows and nonpoint-source pollution to the headwaters of Mill Creek. Additionally, the BMP is replenishing local groundwater supplies and helping maintain baseflow in the local first-order tributaries of Mill Creek. The long-term monitoring being conducted at the site is providing detailed insight into the performance of the BMP. This experience and performance data will be used to better understand and implement similar stormwater BMPs in the future. The extreme design limitations imposed by the relatively small area with numerous utilities show that the infiltration trench BMP is capable of being successfully retrofitted into some of the tightest existing urban conditions. The trench, still only a year old, has been the subject of numerous tours attended by students, professors, regulators, watershed groups, and design engineers.